LP Section
 

Home
Timeline
GenCap
The DC Supplies
LP Section
1920 Plant Specs
MP Section
HP Section
NAGS Control Room
Power System
Picture Gallery
1960's Names

Live Weather

  In 1958 the Low Pressure (LP) boilers were still in situ but when I returned in the summer of 1959 after eleven months at the apprentice training school, East Yelland,  they had been removed. The remaining installed boiler capacity was sufficient for the installed turbine capacity with just a minor adjustment. A pressure reducing range between the HP boilers and LP turbines had been installed. There was already a steam pressure reducing range between the MP boilers and LP turbines.
   
  The LP Stirling boilers constructed between 1920 and 1923 as part of the AC station were numbered 5,6,7 & 8 and the steam turbines nos. 3 & 4. Boilers 1 to 4 formed the original DC generating station.  Boilers 5-8 with an evaporation rate of 25,000 lbs/hr were chain grate with a single Induced Fan per pair of boilers which drew the air for combustion through the moving grate. Coal to the grate was fed via hoppers and chutes but largely controlled by manual labour and all ash handling was via manually hauled trolleys on a system of rails - an horrendous dark and sulphurous atmosphere - dirt was not the word for it. There are no records regarding Boilers 1 to 4 but they will have been entirely hand fired - a very manual process.
   
  The boiler feed pumps were neat small steam turbines which were a real piece of machinery requiring virtually no maintenance. Cooling water to the turbine condensers was fed from the Number 1 Pump house on the River Teign. The cooling water was returned further down stream to the River Teign.
   
  The turbine operating steam pressure was 150 psi with the boilers and steam range target being 165 psi at 540 deg F (282 deg C). The turbines were 3000 rpm British Thomson-Houston (BTH) and rated at 3750 kw connected at 11,000 volts to the cellular switchboard. In the picture below the Electrical Maintenance workshop was behind the windows on the left. I suspect this area included the first control room and below this the 11kv cellular switch gear. 
   
  The roof frames in the distance covered the two 400 kw DC Rotary Convertors and the 500 volt DC Switchboard together with a 500 volt 600 ampere hour battery bank.
   
 

 

The LP Turbine Hall - Generators 3 & 4 - Exciter and Alternator end

   
 

   
 

 

HP Steam end - Governor Gear and Speeder motor

   
  Following the removal of the LP boilers the basement area was converted into a Civil Defence Regional shelter - a serious concrete structure with is own diesel generator and air conditioning. It was never used in anger but provided a base for tools and equipment in the event of a civil emergency.