MP Section
 

Home
Timeline
GenCap
The DC Supplies
LP Section
1920 Plant Specs
MP Section
HP Section
NAGS Control Room
Power System
Picture Gallery
1960's Names

Live Weather

 
  The medium pressure (MP) section of the station was completed in two phases - 1929 and 1931 - and ultimately comprised four boilers and two turbo alternators together with an 11,000 volt metal clad switch room constructed during the second phase. The boilers were nos. 9,10,11 and 12 and the turbines nos. 5 and 6. Note at the time of construction this section was referred to as the High Pressure Section.  
     
  The Boiler operating pressure was 265 psi at 650 deg F (343 deg C) with the turbine inlet at 250 psi. The alternator outputs were 7,500 kw Maximum Continuous Rating (MCR) with an Economic Continuous Rating (ECR) of 6,000 kw and switched at 11,000 volts. The alternators ran at 3000 rpm. Boilers 9 and 10 had an evaporation rate greater than 40,000 lbs/hr whilst boilers 11 and 12 had an evaporation rate of 50,000 lbs per hour. The coal bunkering system was designed to receive two fuel types - coal and coke. The original coal supplies were from the Forest of Deane and coke was a by-product of local coal gas production. The boiler fire comprised a sandwich of the two fuels with coke as the lower.  
     
  Below is a copy of the programme that brings No 6 Machine into commission on the 19th November 1931. (Number 5 machine was fully commissioned on 1st May 1929). At this time the station was still operating as an 'islanded' source of electricity providing supplies to both Newton Abbot and Torquay as well as the China Clay pit areas of the Teign Valley. An interesting fact of the time is that the average annual consumption of electricity per person was little more than twenty units per year. Of course electricity at that time went to the very few but it is an interesting reflection of how things have changed.  
     
     
  Following the commissioning of the second Medium Pressure machine - No 6 - in 1931 a 132,000 volt connection from Exeter and onwards to Plymouth and Hayle was established and the first stage of what we now know as National Grid created in 1934. This single connection meant the station was still at risk of being islanded and was on numerous occasions but started the period of shared spare generating capacity and economic 'merit order' operation.  
     
 

Turbo Alternator Number 6 - Fixed blades and steam rotor

 
     
 

 
 

Turbo Alternator Number 6 - Stator and Rotor

 
     
  Cooling water to supply the MP Turbine condensers was drawn from the Number 2 pump house located on the banks of the River Teign. This pump house also provided top up water for the cooling tower yet to be built and cooling water returned to the River Lemon a confluent of the River Teign.  

 

 

Up Timeline GenCap The DC Supplies LP Section 1920 Plant Specs MP Section HP Section NAGS Control Room Power System Picture Gallery 1960's Names